3.0T核磁共振安装要素及场地准备流程概述
朱 弋,王明书,黄竞宇
【摘要】从机房选址、场地设计及土建施工等方面介绍了核磁共振场地的准备流程,通过对3.0T磁共振安装过程中的
场地、机房、屏蔽、空调、电源、照明、接地等进行阐述,总结出了针对3.0T超导核磁共振的一套较为完整的场地设计准
备安装流程,满足了使用要求,对于核磁共振的安装具有重要的意义。
【关键词】3.0T核磁共振;场地要求;安装
[中国图书资料分类号】TH774【文献标识码]A【文章编号】1003—8868(2011)11-0122—03
Summary of 3.0T MRI S Installation Elements and Site Preparation Procedure
ZHU Yi,WANG Ming—shu,HUANG Jing—vu
(Medical Engineering Department,Kunming General Hospital of Chengdu Military Area Command,Kunming 650032,China)
Abstract rhe new-generation 3.0T MRI system has strong magnet field and high magnet precision.It needs very serious
conditions for the circumstance and shield device.In order to make the whole MRI system work in a normal state,a
normative site preparation and installation procession standard is necessary.The installation elements。such as the site.the
device room,the shield。the conditioner,the illumination and the ground connection,are explained and summarized.Then a
set of entire site preparation and installation procedure standard f0r 3.0T MRI is put forward.[Chinese Medical Equipment
JournaI,201 1,32(1 1):122-123,1261
Key words 3.0T MRI;conditional demand of site;installation
1 核磁共振场地准备流程 1.3屏蔽施工
3.0T核磁共振磁场强度高、磁体精度高,对周围环境及
屏蔽工程的要求非常高。在场地准备过程中,必须严格按照厂
商提供的技术参数和场地要求施工。总体分为以下几个步骤.
见图1
屏蔽施工一般由专业的施工单位来完成,主要包括射频
屏蔽和磁屏蔽。一般采用0.5 mm厚的铜板在机房四周六面
构筑一个密闭无缝的六面体。在机房内的用电设备,如供电照
明、心电监护、高压注射器等均不能采用交流220 V供电.而
要采用电池或直流电源供电。屏蔽工程结束后,要用专业设备
对磁体间进行无源匀场检测ll l
1.4空调和水冷机的安装
水冷机安装在室外,为氦压机和磁体内的梯度线圈提供持
续恒温的冷却水。同时,还必须安装备用自来水管,当水冷机出
现故障不工作时,要用自来水紧急冷却氦压机和梯度线圈.以
防止液氦蒸发,导致失超。
核磁共振系统的控制设备在工作时产生大量的热量,必
图1 核磁共振的场地准备及安装流程
须采用专业恒温、恒湿的高精度空调对其进行温度和湿度的
调整。空调主机安装于设备间,同时有风管连接到磁体间.对
磁体间的温湿度进行调节。
2场地环境要求
1.1 机房选址
核磁共振的机房选址必须遵循以下原则:机房周围附近
不能有大型的变电站或变压器输电机组,必须远离电梯等大
型动力电用电设施,以避免加重屏蔽工程的难度。为了便于磁
体的运输安装,一般将磁共振机房定在医院大楼的一楼。
1.2场地设计及土建施工
系统所在的位置必须保证运行中既没有外部的干扰而影
响磁场的均匀性和系统的正常运行.又要保证人员的安全和
其他敏感设备的功能不受磁场的影响。
在0.5 mT限制区域需要设磁场警告标志,如果磁通密度
在指定区域超过0.5 mT,必须设置警告标志并作限制进入措
施或当地的限制规定。
厂商派场地工程师到现场进行实地勘察,并根据磁体质
计方案,同时交由专业设计单位设计场
2.1 磁场对其他设备的干扰
翻 ! 地照土设建计方、水案电进施行工施方工案。 。医院必须严格按
,
某些设备的功能会受到磁场的影响.所有这些设备和系
统在布局时必须参考该设备最大允许的磁通密度,其取决于
每个设备和系统部件的敏感性,见表1。
(1)静态的干扰,如铁梁、钢筋水泥。特别是磁体下方。其
l
要 目
作者简介:朱弋(1968一),男,云南昆明人,硕士,
2.2外界对磁场的干扰因素、原因和补偿
副主任,高级工程师+主要从事临床医学工程方面的
研究工作,E-mail:zzyy2401@yahoo.eom.cn。
作者单位:65o032昆明 成都军区昆明总医院医
l —r 辐 『/止— —r Fill*甚立c,、
应满足最小间距/最大质量的要求(见表2),而磁体匀场仅能
部分补偿此影g ̄j[21。
・
医疗卫生装备・2011年11月第32卷第11期Chinese Medical Equipment Journal・Vo1.32・No.11・November・2011
质控与安全l Quality Control&Safety -123・
表1 典型设备允许最大磁通密度限制要求
±2 mm。
支撑面承重力分布见图2,分别为
_1 ——
I
l一
一
一
_
l
l ’
1 J
,r
LL 止
团 团
表2干扰类型和最小间距的限制要求
图2核磁共振支撑面示意图(单位:em)
4个支撑面.每个25x25 cm(625 cm ),支撑面1=22.2 kN,
支撑面2=23.5 kN,支撑面3=13.3 kN,支撑面4=20.8 kN。
3.2系统控制机柜
以西门子3.OT核磁共振Magnetom Verio为例,MR系统
共有3个机柜。GPA/ACC重约1 250 kg,SEP重约340 kg,
35 kW射频柜重约500 kg。为避免磁场的干扰,GPA/ACC和
SEP机柜必须放在5 mT磁力线范围以外,35 kW射频功放柜
必须放在1 mT磁力线范围以外。
4电源及地线要求
4.1电源要求
配电设备的安装要符合国家标准.具体指标要求如下 :
电压为380/400(1+10%)V,三相五线制;频率为(50-x_1)Hz;-
线间不平衡最大为 ;接入功率VQ--engine为110 kW;瞬间功
(2)动态的干扰,如运动的铁磁物品。为避免此影响,满足
率为140 kW:线内阻最大为95 mll:主交流接触器最小为100
A。
最小的间距的要求是必须的。最小的间距取决于移动方向和
磁场方向。
磁共振主机供电应该直接从医院主变电站连接至磁共振
主机专用配电箱,不再连接其他负载。辅助设备供电(空调、冷
水机等)另取线路,以避免一些频繁启动的高压设备,如电梯、
电动机、泵、压缩机等对磁共振主机的电源干扰。
为保证电源内阻要求,主电缆线截面积不得小于50 m。。
dB
(3)交流50 Hz工频干扰,如电缆、变压器等。
2.3噪声
磁共振设备运行会产生一定的噪声,各功能间的噪声要
求见表3,应依据当地的法规,做噪声控制处理。
表3各功能间的噪声要求
根据国内电网状况,推荐配备整机UPS或稳压电源,建议容
量为140 kW以上
4_2接地线
应请专业人员设计及安装接地线,系统设备要求绝缘良
2.4建筑物震动 好的专用独立地线。接地电阻要求通常不大于2 n【”。地线应
连接至磁共振专用配电箱。
4.3扫描室内的照明和插座
影Ⅱ向磁体的外部震动和冲击会降低图像质量。在0—5O Hz
频率范围内,由建筑物传给磁体的各个方向最大震动加速度不
能超过一80 dB(g)。
2.5现场检查
直接靠近磁体照明设备的工作寿命会受到磁场的影响。
灯丝会随电源的频率而振荡。因此,要求扫描室采用直流照明
在磁共振的安装准备过程中,对特殊情况,必须对场地是
电灯。直流电源的交流残余波纹应≤5%。不使用调光器。由
磁性物质所构成的用电设备被用在扫描室内会由于磁场的原
否满足设备对场地的基本要求进行检查。该检查可包括磁场、
射频干扰和建筑物震动的检测。同时,还需要对建筑物进行其
他审核,如建筑结构确认、承重确认、现场安装准备的执行和
管理等。
3主要部件质量和尺寸对场地的要求
3.1磁体和检查床
因产生危险,因此建议扫描室内不安装交流插座 。
5冷却水的参数要求
5.1 冷却水水质(见表4)
5.2水冷系统(见表5)
以上所提到的数值是参考于MR系统机柜的输入端。与
水冷机等相关的压力和温度的损耗不计在内。
以西门子3.0T核磁共振Magnetom Verio为例,在液氦达
到70%的情况下,磁体和检查床总重约8 300 kg。因此,扫描
室地面必须是结实的地面及具有充足承重能力,如混凝土,且
6射频屏蔽
6.1 屏蔽要求
承重应符合安装要求并得到建筑设计部门的认可嘲。
具体要求如下(以em为单位,不按比例):
磁体和检查床所在地面(3 mx3 m)的水平误差不得超过
(1)MR扫描室要求要有射频屏蔽。此保护系统防止射频
对外部环境的干扰.同时也防止来自外部环境对磁共振系统
的干扰。 ( 下转第126页 )
・
医疗卫生装备・2011年l1月第32巷第11期Chinese Medical Equipment Journal・Vo1.32・No.11・November・2011
・
1 26・ Quality Control&Safety I质控与安全
机或停机后的一段冷却时间内,防止任何人接触这些器件以及
传热敏感的器件,在这些器件表面明显处张贴高温警告标志。
3.4火灾
法,树立严肃、严格、严密、严谨的工作作风;定期学习防护知
识的理论,用理论指导实践:学习相关的法律法规和管理办
法,一旦发生意外,用法律武器保护自己。
(3)科室制定切实可行的规章制度,正确的机器操作规程。
3.4.1 简介
任何电气都有漏电失火的危险.尤其是直线加速器某些
完备的应急预案,使实际工作中有规可依、有章可循,在制度上
避免事故的发生,增强应急处理能力。科室可以举行相关的预
警演戏,熟悉应急处理程序,并且定期检查急停按钮是否失灵、
各项联锁是否有效
部件(如离子泵等)要保持24 h供电,而且机器上冷却水管、
电路板等不利于电气灭火的组件,更应注意防火。
3.4.2 防护
加速器配套使用的一些设备如稳压电源等,需要医院独自
订购。要选用质量有保证的产品。另外,医院应该提供合适的安
全防火措施,如安装气体灭火系统等。治疗室中和控制台附近
应安放有灭火器。而且这种灭火器必须适合于电气灭火。此外,
应在机房附近显著位置张贴失火时脱离危险区的路线图。
4结论
一
(4)32作人员应坚持定期健康查体和进行个人剂量监测,
旦发现血象异常(如白细胞数量有明显下降)或者身体有不
适的症状,要及时就医,必要时应脱离岗位[qz。工作人员应积
极锻炼身体,提高抵抗力,才能更好地为患者服务。
[参考文献】
[1】曾自力.医用电子直线加速器的质量保证和质量控制fJ].医疗卫
生装备,2010,31(9):116.
综上所述,直线加速器的工作人员不仅面临辐射、高压等
危险i4],还面临着许多潜在的危害,因此,放疗工作人员使用直
线加速器,应做到以下几点:
(1)时刻牢记放射防护3原则,即辐射实践的正当化,放
射防护的最优化.个人剂量限值。这3项基本原则构成了一套
[2】刘沛先,尹晓明,吴化军.医用直线加速器检修中应注意的安全
问题『J].中国医疗器械杂志,1998,22(1):46.
【3]姜秀英.医用电子直线加速器的性能检测与质量保证[J].医疗卫
生装备,2005.26(8):56.
放射防护体系,正当化是最优化过程的前提,个人剂量限值是
最优化的约束条件。所以,放射防护3项基本原则是相互关联
的,要灵活运用。
『41王
[5]陈
洵.医用电子直线加速器在使用中应注意的安全性问题及
跃,杨迎晓,张远.应重视医用直线加速器的防护和安
(收稿:2011-03—16修回:2011一o4—22)
对策Ⅲ.医疗卫生装备,2006,27(11):55.
全『J].中国辐射卫生,2007.16(4):506.
(2)时刻保持高度警惕,加强防护意识。技师和工程师要
定期讨论分析加速器在使用中所存在的安全问题及解决办
(..●上接第123页 ●)
表4循环水水质要求
向当地的制冷剂供应商确认。
(2)磁体冷运离开工厂时液氦面大约是70%。在冷头不
工作的状态下,运输过程中液氦挥发每天约为5.4%,磁体就
位静止后液氦挥发每天约为4.0%。为了尽量减少液氦的挥
发,磁体到达现场后,应使冷头尽快投入工作。
(3)在超导状态下,磁体的液氦面警戒水平为40%。当液
氦面降至40%时,需立即进行液氦补充,否则,一旦失超,会
注:1 bar=10 Pa
损伤磁体。
8结语
(2)射频屏蔽需要的衰减值:90 dB以上,在频率范围15~
128 MHz内。这些值必须在磁共振系统安装之前由专业部门
如果在场地选址、屏蔽施工、土建水电施工及空调、水冷
(如无线电管理委员会等)测量确认。
(3)所有连接进扫描室的管线,如直流照明、氧气管、控制
电线、风管进回风口、失超管等必须通过安装在射频屏蔽上的
机等附属设备的安装过程中不慎重或出现失误.将会导致设
备安装完成后出现不明原因的图像伪影和干扰.从而影响整
个设备的正常验收和使用。为了使整个系统及其辅助设施的
安装满足使用要求,必须总结一套科学、规范的场地设计安装
流程,使核磁共振的采购、安装少走弯路,避免不必要的纠纷。
各种滤波器才能进入。
(4)屏蔽室要通过磁共振系统接地,严禁单独接地。屏蔽
室对地绝缘电阻要求大于100 M0。
6.2失超管
[参考文献】
[1]黄邻彬.3.0T超导磁共振安装探讨【JJ.医疗卫生装备,2008,29
(11):100,102.
(1)超导磁共振有液态氦气用于维持超导状态。正常情况
下有少量挥发,磁体内灌装的氦气由液态转为气态,比例为
1:700(单位:L)。因此,必须有1根足够粗的失超管由磁体上
部的出气孔通向室外大气,长度不能太长,尽量减少直角转
[2】朱弋,阮兴云,徐志荣,等.新一代超导核磁共振安装要素[J】.
芳,刘毅.MR机房选址与环境安全问题的探
医疗卫生装备,2005,26(10):45—46.
弯,而且出气口必须避开人群聚集区域。
(2)失超管必须由非铁磁性金属(如不锈钢管等)制成。
7液氦
[3】陈怀亮,袁
(4】袁
讨『J].安徽医学,2010(10):28—29.
伟.磁共振安装中的若干问题[J].中华I临床医学研究杂志,
(收稿:2011-02—21修回:2011-04—06)
(1)对于超导磁体,液氦(He)和氦气是消耗品。运送这些
2008(5):72.
液体进检查室需要使用专用的容器。容器的大小和质量应该
・
医疗卫生装备・2011年11月第32卷第11期Chinese Medical Equipment Journal・Vo1.32・No.11・November・2011
2024年5月17日发(作者:申凡桃)
・
1 22・ Quality Control&Safety l质控与安全
3.0T核磁共振安装要素及场地准备流程概述
朱 弋,王明书,黄竞宇
【摘要】从机房选址、场地设计及土建施工等方面介绍了核磁共振场地的准备流程,通过对3.0T磁共振安装过程中的
场地、机房、屏蔽、空调、电源、照明、接地等进行阐述,总结出了针对3.0T超导核磁共振的一套较为完整的场地设计准
备安装流程,满足了使用要求,对于核磁共振的安装具有重要的意义。
【关键词】3.0T核磁共振;场地要求;安装
[中国图书资料分类号】TH774【文献标识码]A【文章编号】1003—8868(2011)11-0122—03
Summary of 3.0T MRI S Installation Elements and Site Preparation Procedure
ZHU Yi,WANG Ming—shu,HUANG Jing—vu
(Medical Engineering Department,Kunming General Hospital of Chengdu Military Area Command,Kunming 650032,China)
Abstract rhe new-generation 3.0T MRI system has strong magnet field and high magnet precision.It needs very serious
conditions for the circumstance and shield device.In order to make the whole MRI system work in a normal state,a
normative site preparation and installation procession standard is necessary.The installation elements。such as the site.the
device room,the shield。the conditioner,the illumination and the ground connection,are explained and summarized.Then a
set of entire site preparation and installation procedure standard f0r 3.0T MRI is put forward.[Chinese Medical Equipment
JournaI,201 1,32(1 1):122-123,1261
Key words 3.0T MRI;conditional demand of site;installation
1 核磁共振场地准备流程 1.3屏蔽施工
3.0T核磁共振磁场强度高、磁体精度高,对周围环境及
屏蔽工程的要求非常高。在场地准备过程中,必须严格按照厂
商提供的技术参数和场地要求施工。总体分为以下几个步骤.
见图1
屏蔽施工一般由专业的施工单位来完成,主要包括射频
屏蔽和磁屏蔽。一般采用0.5 mm厚的铜板在机房四周六面
构筑一个密闭无缝的六面体。在机房内的用电设备,如供电照
明、心电监护、高压注射器等均不能采用交流220 V供电.而
要采用电池或直流电源供电。屏蔽工程结束后,要用专业设备
对磁体间进行无源匀场检测ll l
1.4空调和水冷机的安装
水冷机安装在室外,为氦压机和磁体内的梯度线圈提供持
续恒温的冷却水。同时,还必须安装备用自来水管,当水冷机出
现故障不工作时,要用自来水紧急冷却氦压机和梯度线圈.以
防止液氦蒸发,导致失超。
核磁共振系统的控制设备在工作时产生大量的热量,必
图1 核磁共振的场地准备及安装流程
须采用专业恒温、恒湿的高精度空调对其进行温度和湿度的
调整。空调主机安装于设备间,同时有风管连接到磁体间.对
磁体间的温湿度进行调节。
2场地环境要求
1.1 机房选址
核磁共振的机房选址必须遵循以下原则:机房周围附近
不能有大型的变电站或变压器输电机组,必须远离电梯等大
型动力电用电设施,以避免加重屏蔽工程的难度。为了便于磁
体的运输安装,一般将磁共振机房定在医院大楼的一楼。
1.2场地设计及土建施工
系统所在的位置必须保证运行中既没有外部的干扰而影
响磁场的均匀性和系统的正常运行.又要保证人员的安全和
其他敏感设备的功能不受磁场的影响。
在0.5 mT限制区域需要设磁场警告标志,如果磁通密度
在指定区域超过0.5 mT,必须设置警告标志并作限制进入措
施或当地的限制规定。
厂商派场地工程师到现场进行实地勘察,并根据磁体质
计方案,同时交由专业设计单位设计场
2.1 磁场对其他设备的干扰
翻 ! 地照土设建计方、水案电进施行工施方工案。 。医院必须严格按
,
某些设备的功能会受到磁场的影响.所有这些设备和系
统在布局时必须参考该设备最大允许的磁通密度,其取决于
每个设备和系统部件的敏感性,见表1。
(1)静态的干扰,如铁梁、钢筋水泥。特别是磁体下方。其
l
要 目
作者简介:朱弋(1968一),男,云南昆明人,硕士,
2.2外界对磁场的干扰因素、原因和补偿
副主任,高级工程师+主要从事临床医学工程方面的
研究工作,E-mail:zzyy2401@yahoo.eom.cn。
作者单位:65o032昆明 成都军区昆明总医院医
l —r 辐 『/止— —r Fill*甚立c,、
应满足最小间距/最大质量的要求(见表2),而磁体匀场仅能
部分补偿此影g ̄j[21。
・
医疗卫生装备・2011年11月第32卷第11期Chinese Medical Equipment Journal・Vo1.32・No.11・November・2011
质控与安全l Quality Control&Safety -123・
表1 典型设备允许最大磁通密度限制要求
±2 mm。
支撑面承重力分布见图2,分别为
_1 ——
I
l一
一
一
_
l
l ’
1 J
,r
LL 止
团 团
表2干扰类型和最小间距的限制要求
图2核磁共振支撑面示意图(单位:em)
4个支撑面.每个25x25 cm(625 cm ),支撑面1=22.2 kN,
支撑面2=23.5 kN,支撑面3=13.3 kN,支撑面4=20.8 kN。
3.2系统控制机柜
以西门子3.OT核磁共振Magnetom Verio为例,MR系统
共有3个机柜。GPA/ACC重约1 250 kg,SEP重约340 kg,
35 kW射频柜重约500 kg。为避免磁场的干扰,GPA/ACC和
SEP机柜必须放在5 mT磁力线范围以外,35 kW射频功放柜
必须放在1 mT磁力线范围以外。
4电源及地线要求
4.1电源要求
配电设备的安装要符合国家标准.具体指标要求如下 :
电压为380/400(1+10%)V,三相五线制;频率为(50-x_1)Hz;-
线间不平衡最大为 ;接入功率VQ--engine为110 kW;瞬间功
(2)动态的干扰,如运动的铁磁物品。为避免此影响,满足
率为140 kW:线内阻最大为95 mll:主交流接触器最小为100
A。
最小的间距的要求是必须的。最小的间距取决于移动方向和
磁场方向。
磁共振主机供电应该直接从医院主变电站连接至磁共振
主机专用配电箱,不再连接其他负载。辅助设备供电(空调、冷
水机等)另取线路,以避免一些频繁启动的高压设备,如电梯、
电动机、泵、压缩机等对磁共振主机的电源干扰。
为保证电源内阻要求,主电缆线截面积不得小于50 m。。
dB
(3)交流50 Hz工频干扰,如电缆、变压器等。
2.3噪声
磁共振设备运行会产生一定的噪声,各功能间的噪声要
求见表3,应依据当地的法规,做噪声控制处理。
表3各功能间的噪声要求
根据国内电网状况,推荐配备整机UPS或稳压电源,建议容
量为140 kW以上
4_2接地线
应请专业人员设计及安装接地线,系统设备要求绝缘良
2.4建筑物震动 好的专用独立地线。接地电阻要求通常不大于2 n【”。地线应
连接至磁共振专用配电箱。
4.3扫描室内的照明和插座
影Ⅱ向磁体的外部震动和冲击会降低图像质量。在0—5O Hz
频率范围内,由建筑物传给磁体的各个方向最大震动加速度不
能超过一80 dB(g)。
2.5现场检查
直接靠近磁体照明设备的工作寿命会受到磁场的影响。
灯丝会随电源的频率而振荡。因此,要求扫描室采用直流照明
在磁共振的安装准备过程中,对特殊情况,必须对场地是
电灯。直流电源的交流残余波纹应≤5%。不使用调光器。由
磁性物质所构成的用电设备被用在扫描室内会由于磁场的原
否满足设备对场地的基本要求进行检查。该检查可包括磁场、
射频干扰和建筑物震动的检测。同时,还需要对建筑物进行其
他审核,如建筑结构确认、承重确认、现场安装准备的执行和
管理等。
3主要部件质量和尺寸对场地的要求
3.1磁体和检查床
因产生危险,因此建议扫描室内不安装交流插座 。
5冷却水的参数要求
5.1 冷却水水质(见表4)
5.2水冷系统(见表5)
以上所提到的数值是参考于MR系统机柜的输入端。与
水冷机等相关的压力和温度的损耗不计在内。
以西门子3.0T核磁共振Magnetom Verio为例,在液氦达
到70%的情况下,磁体和检查床总重约8 300 kg。因此,扫描
室地面必须是结实的地面及具有充足承重能力,如混凝土,且
6射频屏蔽
6.1 屏蔽要求
承重应符合安装要求并得到建筑设计部门的认可嘲。
具体要求如下(以em为单位,不按比例):
磁体和检查床所在地面(3 mx3 m)的水平误差不得超过
(1)MR扫描室要求要有射频屏蔽。此保护系统防止射频
对外部环境的干扰.同时也防止来自外部环境对磁共振系统
的干扰。 ( 下转第126页 )
・
医疗卫生装备・2011年l1月第32巷第11期Chinese Medical Equipment Journal・Vo1.32・No.11・November・2011
・
1 26・ Quality Control&Safety I质控与安全
机或停机后的一段冷却时间内,防止任何人接触这些器件以及
传热敏感的器件,在这些器件表面明显处张贴高温警告标志。
3.4火灾
法,树立严肃、严格、严密、严谨的工作作风;定期学习防护知
识的理论,用理论指导实践:学习相关的法律法规和管理办
法,一旦发生意外,用法律武器保护自己。
(3)科室制定切实可行的规章制度,正确的机器操作规程。
3.4.1 简介
任何电气都有漏电失火的危险.尤其是直线加速器某些
完备的应急预案,使实际工作中有规可依、有章可循,在制度上
避免事故的发生,增强应急处理能力。科室可以举行相关的预
警演戏,熟悉应急处理程序,并且定期检查急停按钮是否失灵、
各项联锁是否有效
部件(如离子泵等)要保持24 h供电,而且机器上冷却水管、
电路板等不利于电气灭火的组件,更应注意防火。
3.4.2 防护
加速器配套使用的一些设备如稳压电源等,需要医院独自
订购。要选用质量有保证的产品。另外,医院应该提供合适的安
全防火措施,如安装气体灭火系统等。治疗室中和控制台附近
应安放有灭火器。而且这种灭火器必须适合于电气灭火。此外,
应在机房附近显著位置张贴失火时脱离危险区的路线图。
4结论
一
(4)32作人员应坚持定期健康查体和进行个人剂量监测,
旦发现血象异常(如白细胞数量有明显下降)或者身体有不
适的症状,要及时就医,必要时应脱离岗位[qz。工作人员应积
极锻炼身体,提高抵抗力,才能更好地为患者服务。
[参考文献】
[1】曾自力.医用电子直线加速器的质量保证和质量控制fJ].医疗卫
生装备,2010,31(9):116.
综上所述,直线加速器的工作人员不仅面临辐射、高压等
危险i4],还面临着许多潜在的危害,因此,放疗工作人员使用直
线加速器,应做到以下几点:
(1)时刻牢记放射防护3原则,即辐射实践的正当化,放
射防护的最优化.个人剂量限值。这3项基本原则构成了一套
[2】刘沛先,尹晓明,吴化军.医用直线加速器检修中应注意的安全
问题『J].中国医疗器械杂志,1998,22(1):46.
【3]姜秀英.医用电子直线加速器的性能检测与质量保证[J].医疗卫
生装备,2005.26(8):56.
放射防护体系,正当化是最优化过程的前提,个人剂量限值是
最优化的约束条件。所以,放射防护3项基本原则是相互关联
的,要灵活运用。
『41王
[5]陈
洵.医用电子直线加速器在使用中应注意的安全性问题及
跃,杨迎晓,张远.应重视医用直线加速器的防护和安
(收稿:2011-03—16修回:2011一o4—22)
对策Ⅲ.医疗卫生装备,2006,27(11):55.
全『J].中国辐射卫生,2007.16(4):506.
(2)时刻保持高度警惕,加强防护意识。技师和工程师要
定期讨论分析加速器在使用中所存在的安全问题及解决办
(..●上接第123页 ●)
表4循环水水质要求
向当地的制冷剂供应商确认。
(2)磁体冷运离开工厂时液氦面大约是70%。在冷头不
工作的状态下,运输过程中液氦挥发每天约为5.4%,磁体就
位静止后液氦挥发每天约为4.0%。为了尽量减少液氦的挥
发,磁体到达现场后,应使冷头尽快投入工作。
(3)在超导状态下,磁体的液氦面警戒水平为40%。当液
氦面降至40%时,需立即进行液氦补充,否则,一旦失超,会
注:1 bar=10 Pa
损伤磁体。
8结语
(2)射频屏蔽需要的衰减值:90 dB以上,在频率范围15~
128 MHz内。这些值必须在磁共振系统安装之前由专业部门
如果在场地选址、屏蔽施工、土建水电施工及空调、水冷
(如无线电管理委员会等)测量确认。
(3)所有连接进扫描室的管线,如直流照明、氧气管、控制
电线、风管进回风口、失超管等必须通过安装在射频屏蔽上的
机等附属设备的安装过程中不慎重或出现失误.将会导致设
备安装完成后出现不明原因的图像伪影和干扰.从而影响整
个设备的正常验收和使用。为了使整个系统及其辅助设施的
安装满足使用要求,必须总结一套科学、规范的场地设计安装
流程,使核磁共振的采购、安装少走弯路,避免不必要的纠纷。
各种滤波器才能进入。
(4)屏蔽室要通过磁共振系统接地,严禁单独接地。屏蔽
室对地绝缘电阻要求大于100 M0。
6.2失超管
[参考文献】
[1]黄邻彬.3.0T超导磁共振安装探讨【JJ.医疗卫生装备,2008,29
(11):100,102.
(1)超导磁共振有液态氦气用于维持超导状态。正常情况
下有少量挥发,磁体内灌装的氦气由液态转为气态,比例为
1:700(单位:L)。因此,必须有1根足够粗的失超管由磁体上
部的出气孔通向室外大气,长度不能太长,尽量减少直角转
[2】朱弋,阮兴云,徐志荣,等.新一代超导核磁共振安装要素[J】.
芳,刘毅.MR机房选址与环境安全问题的探
医疗卫生装备,2005,26(10):45—46.
弯,而且出气口必须避开人群聚集区域。
(2)失超管必须由非铁磁性金属(如不锈钢管等)制成。
7液氦
[3】陈怀亮,袁
(4】袁
讨『J].安徽医学,2010(10):28—29.
伟.磁共振安装中的若干问题[J].中华I临床医学研究杂志,
(收稿:2011-02—21修回:2011-04—06)
(1)对于超导磁体,液氦(He)和氦气是消耗品。运送这些
2008(5):72.
液体进检查室需要使用专用的容器。容器的大小和质量应该
・
医疗卫生装备・2011年11月第32卷第11期Chinese Medical Equipment Journal・Vo1.32・No.11・November・2011